    HomeBusinessCrabbs LNG Plant Completed but Commissioning Delayed by Harbour Dredging

    Crabbs LNG Plant Completed but Commissioning Delayed by Harbour Dredging

    Published on

    spot_img

    The Antigua Power Company Maintenance and Operations Limited – APCMOL, Antigua Public Utilities Authority – APUA, and Eagle LNG hosted the launch of the first Liquefied Natural Gas (LNG) Fuel Terminal Project in the Eastern Caribbean on Tuesday July 27th, 2021 at the Crabbs Peninsula.

    Antigua’s new Liquefied Natural Gas (LNG) plant at Crabbs is complete but remains idle as the government awaits the completion of critical harbour dredging works, Utilities Minister Melford Nicholas has confirmed.

    The project, which is already over a year and a half behind schedule, cannot be commissioned until dredging in Parham Sound reaches the required depth to accommodate large LNG tankers. The dredging is expected to be completed within the next three and a half months.

    “The plant is completed, but it hasn’t been able to be commissioned,” Nicholas said. “The dredging of the harbour has been our Achilles’ heel.”

    In the meantime, the facility has operated briefly on diesel fuel, but the Minister warned that doing so dramatically increases operational costs—adding as much as $2 million per month to energy expenses.

    To address the delay, two dredging teams—Blue Ocean and Dutch Dredging—are currently working to deepen the harbour to approximately eight metres, allowing for the safe docking of LNG vessels. Nicholas said this is a crucial step to bring the plant fully online and begin supplying cleaner, more affordable fuel to the national grid.

    The LNG facility is part of the government’s broader energy strategy, aimed at reducing dependence on heavy fuel oils and lowering overall electricity generation costs. Once operational, it is expected to provide a more efficient and environmentally friendly energy source while supporting Antigua and Barbuda’s transition toward a more sustainable energy future.

    Latest articles

    Antigua and Barbuda set to Ratify Treaty of San Jose at upcoming sitting of Parliament.

    Attorney General the Hon. Sir Steadroy Benjamin made the announcement during his keynote speech...

    NOTICE: Night Road Works

    NOTICE OF NIGHT WORKSThe Ministry of Works wishes to advise the general public that...

    Buckleys Storage Tank Nearing Completion of Refurbishments; New Reservoir Planned for New Winthorpes

    Utilities Minister Melford Nicholas has confirmed that restoration work on a key water storage...

    New Barnacle Point Desalination Plant Set to Begin Operations by Late October

    Utilities Minister Melford Nicholas has confirmed that a second desalination facility at Barnacle Point...

    More like this

    Antigua and Barbuda set to Ratify Treaty of San Jose at upcoming sitting of Parliament.

    Attorney General the Hon. Sir Steadroy Benjamin made the announcement during his keynote speech...

    NOTICE: Night Road Works

    NOTICE OF NIGHT WORKSThe Ministry of Works wishes to advise the general public that...

    Buckleys Storage Tank Nearing Completion of Refurbishments; New Reservoir Planned for New Winthorpes

    Utilities Minister Melford Nicholas has confirmed that restoration work on a key water storage...