A proposed 55-megawatt solar and battery project must undergo a competitive procurement process before a supplier is selected, Utilities Minister Melford Nicholas says.
Speaking on Taking Stock on Pointe FM on Nov. 10, Nicholas described reports about discussions with visiting Chinese suppliers as premature, saying officials had not yet established the project’s purchasing requirements.
“We had some visiting suppliers from out of China that made certain offers,” he said. “But I don’t think that we were ready for that type of conversation about negotiating rates.”
Nicholas said the proposed installation, planned for the Potworks Dam basin, would require technical and financial assessment before the government could move forward.
“A project of that magnitude has got to go through the national procurement rules,” he said. “It has got to go through the whole tendering process.”
He outlined a possible process involving invitations for expressions of interest, qualification of prospective suppliers and a shortlist of three or four vendors for selective tendering.
Nicholas said he expected officials to prepare a plan for Cabinet’s consideration within roughly 90 to 120 days. He did not announce a contract award or construction start date.
The minister said the proposal would support APUA’s return to generating its own electricity and reduce the country’s exposure to international fuel price fluctuations.
The project’s final cost, equipment requirements and financing arrangements had not been established in his remarks.
This article was originally published by Antigua News Room. Read the original article here: Proposed 55-megawatt solar project in Antigua and Barbuda must go through tendering, minister says.